What Is an EPC Contract and How Does It Allocate Risk?

What Is an EPC Contract and How Does It Allocate Risk?

How engineering, procurement and construction contracts work, who carries the risk and how EPC differs from EPCM

An EPC contract is an agreement in which one contractor takes responsibility for the engineering, procurement and construction of a project and hands it over ready to operate. EPC stands for engineering, procurement and construction. The owner gets a single point of responsibility, usually for a fixed price and a fixed completion date, and the contractor takes on most of the design and delivery risk. That is why EPC contracts are common for power plants, refineries, oil and gas facilities and other large industrial projects.

What does the EPC contractor do?

  • Engineering: develops the detailed design from the owner's requirements, often starting from a front-end engineering design (FEED).
  • Procurement: buys equipment and materials, manages suppliers and arranges logistics.
  • Construction: builds, installs, tests and commissions the facility.

Because the work is often delivered "turnkey", the owner should be able to start operating the plant once it has passed the agreed performance tests.

How does an EPC contract allocate risk?

The main attraction for owners is that most risk sits with the contractor:

  • Price: usually a lump sum, so cost overruns are largely the contractor's problem.
  • Time: a fixed completion date, backed by delay liquidated damages if it is missed.
  • Performance: guarantees on output, efficiency or emissions, backed by performance liquidated damages.
  • Design: the contractor is responsible for the design being fit for its purpose.

Contractors price this risk into their bid, so EPC contracts are rarely the cheapest option on paper. Owners pay for certainty.

How is EPC different from EPCM?

Under an EPCM (engineering, procurement and construction management) arrangement, the contractor designs the project and manages procurement and construction on the owner's behalf, but the owner signs the construction and supply contracts directly. The EPCM contractor is paid for its services rather than for delivering a finished plant, so the owner keeps much more of the cost and schedule risk in exchange for more control and flexibility.

Which standard forms are used?

Many international EPC projects use standard forms rather than writing a contract from scratch. The best known is the FIDIC Silver Book, the Conditions of Contract for EPC/Turnkey Projects, which places most risk on the contractor. Where the owner wants to keep more control over the design, the FIDIC Yellow Book for plant and design-build is often used instead. Whatever form is chosen, the particular conditions and the owner's requirements are where most disputes begin, so they deserve careful drafting.

What do contract managers need to watch?

  • clear, complete owner's requirements and performance tests
  • change order procedures and how variations are valued
  • notice periods and time bars for claims
  • liquidated damages caps and the overall limitation of liability
  • interfaces between the contractor's scope and work kept by the owner

What happens at handover?

Handover on an EPC project usually happens in stages. Mechanical completion confirms that the plant has been built and installed as designed. Pre-commissioning and commissioning follow, as systems are tested, cleaned and brought into operation. The performance tests then check that the plant meets the guaranteed output and efficiency. Once these are passed, the owner takes over the plant, and a defects period begins, during which the contractor must put right any defects that appear. Under FIDIC forms, this is called the Defects Notification Period.

What security does an owner usually ask for?

  • Performance security: a bank guarantee or bond, often a percentage of the contract price, that the owner can call if the contractor fails to perform.
  • Advance payment guarantee: protects any up-front payment made to help the contractor mobilise.
  • Retention: a share of each payment held back until completion or the end of the defects period.
  • Parent company guarantee: a promise from the contractor's parent company to stand behind its obligations.

These protections cost the contractor money, which is reflected in its price, so owners should ask for what they need rather than everything available.

Why do EPC projects still end in disputes?

Even with risk placed on the contractor, disputes are common. Typical causes include owner's requirements that are vague or contradict each other, ground or site conditions that differ from what was expected, variations that are instructed informally and valued later, and delays caused partly by both parties. Owner-supplied equipment or information that arrives late is another frequent source of claims. Clear requirements, disciplined change control and good records prevent many of these problems.

Is EPC right for every project?

No. EPC works best when the owner can define what it wants clearly and is willing to pay a premium for price and time certainty. If the design is still immature, the owner wants a strong say in technical choices, or the project has unusual risks that no contractor will price sensibly, other models may suit better. These include EPCM, traditional design-bid-build, or collaborative approaches such as alliancing.

Where to start

Coventry Academy's Engineering, Procurement and Construction (EPC) Contracts course is designed for professionals who prepare, negotiate or manage EPC contracts. For related subjects, browse our contracts management training courses. Coventry Academy is certified to ISO 9001:2015 and ISO 29993:2017.

Sources

Our In Demand Training Subjects

The subjects professionals book most often, from leadership and project management to oil and gas, finance and AI.